AFPM Core OEM Sourcing & Supplier RFQ

Screen AFPM core OEM sourcing paths and prepare a copyable RFQ checklist. Compare material, tooling and delivery scope; confirm prices, schedules and approval requirements with the supplier.

Request engineering review

Screen a sourcing path & prepare your OEM RFQ

Choose geometry, material and scope for a sourcing checklist. Tooling estimates are subject to part CAD review; prices and schedules remain unknown until quoted.

Candidate path: Pilot validation: smc. Supplier evidence and customer release required.
AFPM Core OEM Sourcing Inputs. All fields are required.

1–500000 motor sets/year; whole numbers. Define parts per set in the RFQ.

40–600 mm. Envelope only; individual part geometry is still required.

All fields are required. Development phase is independent of annual volume. The screen does not test material/topology compatibility or calculate press capacity, prices or approval duration.

Try six illustrative application presets
Static default: YASA, SMC, pilot phase, automotive quality planning.
Candidate tooling path: Trial a dedicated compaction die and qualify density, ejection and heat-treatment controls before scaling.Schedule: Unknown — request dated tooling, sampling and approval milestones · Tooling NRE: Unknown — supplier CAD/DFM quotation required · Unit cost: Unknown — define parts per motor set and delivery scope
Tooling & Schedule

Unknown — request dated tooling, sampling and approval milestones

Trial a dedicated compaction die and qualify density, ejection and heat-treatment controls before scaling.

Commercial inputs to confirm

Unknown — define parts per motor set and delivery scope

Tooling NRE: Unknown — supplier CAD/DFM quotation required

Quality Gate

Customer PPAP level to confirm

Agree applicable records, test methods, sampling and acceptance criteria with the customer. This checklist does not establish certification or part approval.

Sourcing path: inputs → supplier evidence → engineering review

Geometry candidate

Yokeless segmented teeth

Process discussion

Pilot validation: smc

Scope and evidence

insulated subassembly · automotive planning

1,200 motor sets/year · pilot phase · smc. Material suitability, capacity and customer release remain to confirm.

Primary Quality & Compliance Deliverables

  • Verify IATF 16949 certificate scope and customer-specific requirements; agree the PPAP submission level (Level 3 is a planning example).
  • Agree PFMEA, control plan, MSA and initial capability criteria with customer quality; thresholds are not calculated here.
  • Document lot traceability, material declarations where required and customer release status.

Technical Risks & Audit Focus

  • Risk: Density gradients and ejection cracks at section transitions
  • Risk: Machining and heat treatment can change particle insulation and core loss
  • Risk: Validate tooth retention from hot/aged assembly loads, asymmetric gaps and fault cases; no universal per-tooth force applies.
  • Audit: Powder grade, storage requirements and lot traceability
  • Audit: Press force, fill/ejection control and grade-specific heat-treatment records
View or manually copy the complete RFQ data package brief
Request engineering review with this RFQ brief

By AxialFluxCore · First recorded · Evidence reviewed .

Annual editorial review, with earlier revisions when material or standards evidence changes. Public source scopes were checked on the review date. Licensed clauses, project compliance, supplier capacity and commercial offers have not been independently audited.

Evidence policy: references support only their stated method or scope. Procurement worksheets, process paths and scenarios are editorial guidance. No supplier pricing dataset is used; lead times, costs and acceptance values remain unknown until agreed for your project.

Five Strategic Decisions Before Issuing an AFPM Core RFQ

Define one comparable motor set

List each part and quantity, drawing revision and delivery scope before comparing offers. The tool brief records open items for supplier review.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Qualify insulation at system level

Converter-fed Type I winding-system tests depend on the actual electrical stress. Bare-core material selection cannot set a universal PDIV limit.

Scope references (editorial actions require project validation): IEC 60034-18-41:2014+AMD1:2019 — Type I insulation systems

Reproduce the default sourcing screen

Select YASA, SMC, pilot phase, 1,200 motor sets/year, 220 mm OD, automotive quality and insulated subassembly, or use Reset defaults. The candidate path requests compaction-die trials and process validation. Schedule, tooling NRE and unit price remain unknown. This is a reproducible software example, with no supplier or hardware performance claim.

AFPM core OEM sourcing tool with default YASA SMC pilot inputs and candidate sourcing path
AxialFluxCore production-build software capture, 2026-11-05, Chromium at 1200 × 900 pixels, default inputs. Reset the tool to reproduce this screen; this is not a customer case study.

1. Separate a procurement screen from part approval

This tool organizes buyer inputs and supplier questions. It cannot qualify a vendor or determine a commercial price.

Begin with the part boundary: individual tooth, bonded stack, annular core, insulated component or complete wound stator. Define a motor set by listing the quantities and revisions of each part. Without this definition, two quotations labelled “per set” can cover different work.

The model selects a discussion path from the chosen process and development phase. Annual volume and stator-envelope OD are recorded in the brief, not used to calculate press force, cavitation, magnetic loss or price. This distinction lets procurement request comparable evidence without treating missing engineering inputs as measured results.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Sourcing stage gates

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Sourcing stage gates: Define scope — CAD, BOM and duty — Unknowns assigned; Request evidence — Route and test plan — Comparable offers; Review and release — Engineering and quality — Customer approval

Recommended procurement action: Agree the BOM, drawing revision and responsibility split before requesting comparable quotes.

2. Topology is a geometry question, not a material verdict

Stator/rotor count alone does not determine whether back iron, powder compaction or a particular tooling process is required.

Yokeless segmented armatures use separate teeth without a common stator yoke. SSDR describes one stator and two rotors and can include a yokeless design; it does not imply a continuous slotted ring. DSSR describes two stators around one rotor, but the actual return-flux path and mounting layout must still be supplied.

A slotless stator can retain magnetic back iron, while a fully coreless stator has no magnetic stator core. The tool covers the former. For a coreless concept, send the coil, rotor and support requirements for engineering review instead of treating the selected core material as a recommendation.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 1: Topology and scope boundaries
TopologyKnown from labelStill required
YASAYokeless segmented armatureRetention load path and actual tooth geometry
SSDROne stator, two rotors; may be yokelessCross-section and back-iron/flux path
DSSRTwo stators, one rotorBoth gaps and mounting/load paths
Slotless with back ironNo stator teeth; magnetic backing retainedBacking geometry, strip/grade and coil support
Fully corelessNo magnetic stator coreOutside this tool: review coils, rotor and supports

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Attach a cross-section showing flux direction, magnetic back iron, gaps and support interfaces.

3. Compare material candidates at matched conditions

A family label is insufficient to rank magnetic loss, permeability, cost or mechanical strength.

Request the exact grade, specimen preparation, frequency, peak flux density, temperature and excitation waveform for each candidate. Separate B at a stated field from saturation polarization: the two are not interchangeable. Ask how supplier curves correlate with the actual machined, pressed or stacked part.

For one concrete process example, Höganäs specifies 600–800 MPa compaction and N2 heat treatment at a maximum 650°C for Somaloy 5P. Its process study shows why processing history matters. These conditions are not a recipe for all powders, and they do not establish a finished-tooth strength guarantee.

Scope references (editorial actions require project validation): Höganäs Somaloy 5P — manufacturer process guidance · Höganäs — effect of manufacturing processes on coated SMC

SMC process evidence chain

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

SMC process evidence chain: Material recipe — Exact grade and lot — Supplier-qualified inputs; Compaction / heat — Fill, ejection and recipe — Recorded process controls; Delivered component — Loss, geometry, strength — Correlated acceptance

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 2: Material comparison evidence to request
CandidateProcess issueRequired comparison evidence
SMCDensity and particle insulation after processingExact grade, B-H/loss curves and finished-part correlation
Tape-wound GOESRolling direction, cut edges and stressGrade, orientation, post-cut loss and stack dimensions
Segmented NOESBurrs, stacking and bondingSheet thickness/coating, stack factor and finished-stack loss
Amorphous ribbonBrittleness and stress sensitivityAlloy, handling/annealing route and encapsulated performance

Scope references (editorial actions require project validation): Höganäs — effect of manufacturing processes on coated SMC

Recommended procurement action: Compare measured grade-specific curves and post-process samples; keep unmeasured values marked unknown.

4. Choose tooling by revision risk and validated economics

A prototype/pilot/series phase is independent of annual volume; there is no universal break-even volume.

Compare a development tool or supplier-qualified blank route with production tooling. Ask whether blank machining is feasible for the actual geometry and coating system, and how it changes loss, strength and surface insulation. A machined prototype is not automatically representative of a later pressed production part.

For a like-for-like quantity basis, break-even quantity equals extra fixed investment divided by the positive per-unit saving. Include maintenance, qualification, yield and revision risk; if the unit saving is zero or negative, the simple model has no positive break-even. Quotes and schedules must come from dated supplier offers.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Tooling investment decision

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Tooling investment decision: Prototype route — Geometry changes likely — Verify processed parts; Pilot route — Demonstrate repeatability — Compare fixed costs; Series route — Prove yield and capacity — Release tool investment

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 3: Tooling route comparison worksheet
PhaseCandidate routeCommercial unknownRelease evidence
PrototypeQualified blank/development toolingPrice and completion date: supplier quoteGeometry and post-process properties demonstrated
PilotDedicated tooling trialsNRE, yield and sampling: supplier quoteRepeatable process and correlated inspection
SeriesCapacity/cavity optionsMaintenance, rate and piece price: supplier quoteCustomer-approved process and capacity

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Request two route-specific offers with identical part scope, lifetime quantity and acceptance requirements.

5. Audit the actual process and its subcontractors

Capability evidence must match the selected material and delivery scope.

For SMC, inspect powder handling, fill/ejection controls and grade-specific thermal processing. For laminated steel, inspect strip traceability, burrs, stacking and bonding. For ribbon, inspect handling, heat treatment and stress control. A powder press is not a prerequisite for a lamination supplier.

Use a competent auditor with the contracted VDA 6.3:2023 edition and current interpretations when required. This playbook does not map powder-specific checks to official starred question numbers or calculate downgrade rules. An audit rating is evidence for a sourcing decision, rather than automatic customer production approval.

Scope references (editorial actions require project validation): VDA 6.3:2023 — official sanctioned interpretations and FAQs

Supplier capability and responsibility

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Supplier capability and responsibility: Actual process — Material-specific operations — Identify subcontractors; Evidence trail — Logs and calibration — Trace to delivered lot; Customer review — Resolve open findings — Agree approval scope
VDA audit preparation boundary

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

VDA audit preparation boundary: Contracted edition — VDA 6.3:2023 if required — Current interpretations; Competent audit — Applicable question set — Licensed scoring rules; Sourcing decision — Close material findings — Separate customer release

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 12: VDA 6.3 audit preparation — editorial mapping
Process concernEvidence to prepareScoring boundary
Project deliveryTool and sample milestones with escalation ownersUse contracted manual/edition
DevelopmentValidation evidence for actual material/processAuditor determines applicable questions
ProductionTraceable material, process and inspection recordsNo invented powder-specific starred numbering
Customer responseContainment and change-control recordsCustomer conditions govern nomination/release

Scope references (editorial actions require project validation): VDA 6.3:2023 — official sanctioned interpretations and FAQs

Recommended procurement action: Review process records and qualified external-laboratory arrangements, including outsourced steps.

6. Agree automotive submission and customer release

Quality planning requires customer agreement on the submission package and acceptance criteria.

Confirm certificate validity, site scope and applicable customer-specific requirements independently from the part approval package. Use Level 3 as a discussion example only; the customer determines the required submission level and applicable evidence.

Request a process flow, PFMEA, control plan, measurement-system evidence, dimensional/material results and capability studies as applicable. Define characteristics, sampling, statistical index, study conditions and limits with customer quality. Do not assign a universal Cpk, Ppk, sample size or signatory to every core.

Scope references (editorial actions require project validation): AIAG PPAP-4 — Production Part Approval Process · IATF 16949:2016 — official publications and customer requirements

Part approval evidence flow

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Part approval evidence flow: Plan with customer — Submission level — Applicable records; Validate process — PFMEA, controls and MSA — Agreed studies/results; Obtain disposition — Customer review — Approved release scope

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 5: Customer approval package planning
Record groupAFPM-specific contentWho confirms acceptance
Design recordsControlled CAD, BOM, datums and magnetic targetsCustomer design authority
Process flow / PFMEA / control planMaterial-specific operations, failure modes and controlsCustomer and supplier quality
MSA and capabilityAgreed characteristics, study conditions and indicesCustomer quality
Results and releaseDimensional/material results and submission dispositionAuthorized customer representative

Scope references (editorial actions require project validation): AIAG PPAP-4 — Production Part Approval Process

Recommended procurement action: Obtain a customer-approved submission checklist and release authority before production shipment.

7. Derive dimensional limits from the assembly stack

A flatness value and a runout measurement represent different geometric conditions.

Start from the minimum operating clearance and account for rotor deflection, bearing motion, thermal growth, coating, assembly error and measurement uncertainty. Allocate a tolerance budget to the relevant part and assembly features rather than copying a generic pole-face value.

The controlled drawing must identify the governing GD&T system, datum features, measurement state and agreed inspection method. A granite plate is a fixture surface, not automatically the datum feature of the part. Ask the supplier to demonstrate that the chosen method resolves the stated tolerance.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Part datums and inspection fixture

Schematic, not to scale. A part datum feature and the inspection fixture are different; tolerance values come from the controlled drawing. Scroll horizontally on narrow screens.

Part datums and inspection fixture: Schematic, not to scale. A part datum feature and the inspection fixture are different; tolerance values come from the controlled drawing.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 6: Drawing-linked inspection plan
CharacteristicSpecify on drawing/planAvoid assuming
Pole-face flatnessGeometric tolerance, state and samplingTIR is identical to flatness
Tooth/assembly heightDatum, assembly condition and uncertaintyOne universal height tolerance fits every gap
OrientationDefined datum features and applicable GD&TFixture surface automatically defines part datum
Surface/edge conditionFinish, radius and insulation interface requirementsVisual smoothness proves magnetic/electrical performance

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Approve a drawing-linked inspection plan with engineering and supplier metrology.

8. Match magnetic methods to material and specimen

Measurement standards define methods; the drawing or purchase specification defines acceptance limits.

IEC 60404-4 covers DC ring/permeameter methods. IEC 60404-6 covers AC ring testing for its listed metallic and powder materials and excludes electrical steels. For steel sheet/strip, discuss the appropriate electrical-steel method such as IEC 60404-2 with the laboratory. ASTM A772 is an impedance-permeability method, not a generic SMC loss specification.

A companion ring can track a powder lot and thermal process, but it does not reproduce every density gradient, cut edge, winding stress or heat-flow path of the delivered component. Establish correlation to finished parts, and record specimen geometry and process conditions. ISO 3325:2026 is a sintered-metal strength method; applicability to heat-treated non-sintered SMC must be agreed.

Scope references (editorial actions require project validation): IEC 60404-4 — DC magnetic measurement methods · IEC 60404-6:2018 — AC ring measurement methods · IEC 60404-2 — electrical steel sheet/strip measurement · ASTM A772/A772M-00(2022) — AC impedance permeability · ISO 3325:2026 — transverse rupture strength of sintered metals

Ring measurement signal path

Conceptual circuit for a suitable ring specimen. The laboratory selects method, excitation, winding and compensation details for the material. Scroll horizontally on narrow screens.

Ring measurement signal path: Conceptual circuit for a suitable ring specimen. The laboratory selects method, excitation, winding and compensation details for the material.
Companion ring correlation

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Companion ring correlation: Companion specimen — Trace lot and processing — Record ring dimensions; Repeatable measurement — Calibrated lab method — Compare matched conditions; Component validation — Geometry / finishing effects — Confirm lot release plan

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 7: Material-specific test matrix
MeasurementCandidate methodBoundary / acceptance owner
DC propertiesIEC 60404-4Use agreed field points and material limits
AC powder/covered alloy ring lossIEC 60404-6Excludes electrical steels; agree frequency, B and temperature
Electrical steel sheet/stripIEC 60404-2Establish correlation to cut and assembled core
Strip impedance permeabilityASTM A772Sinusoidal current; not a generic SMC loss test
Mechanical TRSISO 3325:2026 where applicableSintered-metal scope; agree method for non-sintered SMC

Scope references (editorial actions require project validation): IEC 60404-4 — DC magnetic measurement methods · IEC 60404-6:2018 — AC ring measurement methods · IEC 60404-2 — electrical steel sheet/strip measurement · ASTM A772/A772M-00(2022) — AC impedance permeability · ISO 3325:2026 — transverse rupture strength of sintered metals

Recommended procurement action: Agree a material-specific test matrix and finished-part correlation before lot release.

9. Treat potting as a thermal and mechanical process

Thermal conductivity alone cannot establish retention strength or insulation reliability.

Compare candidate systems using named product data, test temperature, cure schedule, viscosity, bond preparation and ageing conditions. A high filler loading can improve heat conduction while making narrow-gap filling harder. A compliant compound may reduce stress but require a separate structural retention feature.

Define void acceptance by defect location and electrical, thermal or structural consequence. Demonstrate filling and cure on representative assemblies, using sectioning or validated inspection where appropriate. UL insulation-system context can inform material compatibility, but does not set a universal void percentage or resin shear limit.

Scope references (editorial actions require project validation): UL Solutions — electrical insulation systems and UL 1446

Potting qualification trade-offs

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Potting qualification trade-offs: Select materials — Resin, liner and wire — Compatibility evidence; Validate assembly — Filling, cure and interfaces — Thermal / electrical duty; Control production — Defect-specific limits — Agreed inspection plan

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 8: Potting and support trade-offs
CandidatePotential benefitEvidence still required
Rigid filled resinHeat flow and bonded supportProduct-specific hot/aged bond and thermal stress data
Compliant encapsulantStress relief and dampingSeparate retention path and insulation qualification
Molded carrier / mechanical captureDefined assembly supportCreep, fit, cooling and dielectric validation

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Validate the complete material stack and manufacturing route under the intended duty cycle.

10. Validate retention under asymmetric and aged conditions

There is no universal magnetic pull force or proof load per tooth.

The simple pressure expression B²/(2µ0) assumes an idealized field normal to a surface. Force also needs effective area and field distribution; two air-gap forces do not necessarily produce the same net load. It is unsuitable as a stand-alone fatigue or retention qualification.

Engineering must evaluate gap asymmetry, faults, vibration, thermal expansion and hot/aged bond properties. Select mechanical capture and assembly tests for the actual load path. The approved test plan must define load direction, temperature, conditioning, sample count, failure criterion and justification for proof or fatigue margin.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Tooth retention load paths

Schematic, not a force calculation. Evaluate attraction on both faces, net imbalance, internal loads and hot/aged support behaviour. Scroll horizontally on narrow screens.

Tooth retention load paths: Schematic, not a force calculation. Evaluate attraction on both faces, net imbalance, internal loads and hot/aged support behaviour.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 13: Retention design and test evidence
Load pathPotential failureRequired validation
Bonded toothHot/aged debonding or creepRepresentative conditioning and load directions
Mechanical captureContact stress, fatigue or tolerance lossStructural analysis plus assembly testing
Housing/rotor systemGap asymmetry or thermal deflectionOperating/fault load cases and minimum clearance

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Obtain structural analysis and an agreed assembly retention test plan before supplier nomination.

11. Specify converter-fed insulation as a system

DC-bus voltage alone cannot establish PDIV or dielectric withstand test settings.

IEC 60034-18-41 addresses qualification and quality control of Type I winding insulation systems supplied by voltage-source PWM converters. Its scope concerns representative insulation systems or machines, not certification of an unassembled bare core.

Collect motor-terminal waveform data, rise time, cable configuration, temperature and altitude. The responsible electrical engineer must select applicable system tests and distinguish qualification from routine testing. Coating thickness, corner treatment and production limits need validation on the selected stack; no fixed 800 V PDIV or Hi-Pot value is generated here.

Scope references (editorial actions require project validation): IEC 60034-18-41:2014+AMD1:2019 — Type I insulation systems

Converter stress and insulation interfaces

Conceptual layers, not to scale. Test settings depend on the terminal waveform and complete insulation system; no voltage rating is implied. Scroll horizontally on narrow screens.

Converter stress and insulation interfaces: Conceptual layers, not to scale. Test settings depend on the terminal waveform and complete insulation system; no voltage rating is implied.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 14: Insulation qualification responsibilities
RequirementRequired inputResponsible decision
Converter stressTerminal waveform, cable, rise time and repetitionCustomer electrical engineer / lab
System selectionWire, liner/coating, resin and interfacesInsulation-system qualification
Production controlAgreed routine tests and traceabilityCustomer-approved control plan
Material compatibilityActual stack and thermal environmentApplicable system evidence; no universal voltage limit

Scope references (editorial actions require project validation): IEC 60034-18-41:2014+AMD1:2019 — Type I insulation systems · UL Solutions — electrical insulation systems and UL 1446

Recommended procurement action: Agree waveform, insulation class and system/routine test plans with the customer and test laboratory.

12. Prepare a controlled RFQ technical package

Comparable quotations require scope, acceptance, timing and responsibility definitions.

Attach the controlled CAD and drawing revision, individual part mass and quantity per motor set, magnetic targets with test conditions, mechanical/thermal environment and delivery boundary. Identify who owns insulation, winding, potting and assembly validation.

Use the copyable tool brief as an open-items checklist. It does not contain uploaded CAD or validated specifications. Ask each supplier to list exclusions, assumptions, subcontracted operations and the work needed to close each unknown.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 9: RFQ completeness checklist
InputRequired detailReason
GeometryDrawing revision, part mass and quantities per motor setComparable scope and tooling review
Magnetic targetGrade, B-H/loss and test conditionsMaterial and process selection
Mechanical/thermal dutyLoads, gaps, temperatures, cooling and ageingAssembly and process validation
Electrical scopeInsulation stack and motor-terminal conditionsAppropriate system testing
Quality and scheduleCustomer package, quantities, milestones and releaseQualification resources and realistic timing

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Copy the RFQ checklist, complete its open items and attach controlled files through your agreed inquiry process.

13. Compare landed cost on one quantity basis

A should-cost discussion is useful even when current prices are unknown.

For an accepted motor set, include gross material input, material price, cycle/cavity productivity, thermal processing, secondary operations, yield/scrap, inspection, packaging and delivery. State currency, offer date, validity, quantity basis and treatment of tooling NRE.

Do not double-count tooling by paying it upfront and amortizing it again in every piece. Compare suppliers with and without separately charged qualification and logistics. Cost shares and tooling life are unknown until supported by the supplier process plan and commercial offer.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Comparable accepted-set cost

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Comparable accepted-set cost: Same quantity basis — BOM and accepted yield — Currency and offer date; Itemized cost — Material and conversion — NRE and qualification; Landed comparison — Packaging and delivery — Avoid double amortization

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 10: Comparable landed-cost inputs
Cost termSupplier evidenceComparison rule
MaterialGross input mass, grade price and scrap treatmentSame accepted motor-set BOM
ConversionCycle, cavities, rate and yieldSame process and inspection scope
ToolingNRE, maintenance and amortization termsAvoid duplicate recovery
QualificationTests, reports and customer supportSeparate one-time and recurring work
DeliveryPackaging, freight, duties and delivery termsSame destination and responsibility split

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Request an itemized quotation and compare total cost at the same accepted-set quantity.

14. Qualify a backup instead of assuming interchangeability

A second powder or production site requires technical and customer change approval.

Matching family names or nominal density does not prove equivalence. Compare magnetic curves, mechanical properties, insulation, thermal processing and the delivered assembly response. Establish what tests and approval are required before a substitute can be used.

A backup tool may not fit a second press without adapters or new kinematics. Verify platen/tonnage interfaces, utilities, inspection capability and qualification time. Size buffer stock from actual recovery time and demand variability rather than a universal number of days.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Backup supply readiness

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Backup supply readiness: Alternative source — Material, tool and site — Identify shared upstream; Validate transfer — Press fit and process — Demonstrate equivalence; Approve change — Customer requalification — Recovery-based buffer

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 11: Backup supply qualification
RiskMitigationEvidence before release
Material interruptionQualify a second gradeMagnetic, mechanical and assembly equivalence
Tool failureSpares and alternative toolingFit and commissioning at the intended press
Site outageApproved backup process/siteCapacity, controls and customer approval
Delivery disruptionRecovery-based stock policyDemand variability and measured replenishment time

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Run a documented change/requalification exercise for the backup material, tool and site.

15. Make maintenance and transfer rights explicit

Paid tooling does not by itself define ownership, design access or transfer feasibility.

Agree title, asset identification, permitted use, maintenance responsibility, spares, drawing access and transfer support in the purchase terms. Have the responsible commercial/legal team review the agreement for the relevant contract.

Set inspection and refurbishment intervals from wear trends and resulting part quality. Die-material labels alone cannot guarantee stroke life. Record cavity-specific output and stop criteria, and confirm the time and evidence needed for a new-site approval.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 15: Tool maintenance and transfer plan
Asset / activitySupplier evidenceTerm to agree
Tool identityAsset ID, cavity and part revisionsOwnership and permitted use
Wear controlShot count linked to dimensional/quality trendsInspection/refurbishment stop criteria
SparesReplaceable components and drawingsAvailability and cost responsibility
TransferPress interfaces and qualification planAccess, support and customer change approval

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Agree a tool asset register, wear-monitoring plan and practical transfer/requalification procedure.

16. Use evidence gates before weighted scoring

Commercial scoring should follow closure of technical and customer-release gaps.

Before scoring, identify non-negotiable drawing, material, traceability and customer conditions. Mark each supplier response as demonstrated, open or unsupported. Escalate open safety or qualification requirements to the responsible engineering/quality owner.

Agree scorecard weights for the program before reviewing bids. Record the evidence behind each score and keep actions with owners and due dates. A good commercial score does not override a failed requirement or substitute for customer release.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Supplier decision gates

Read left to right; scroll horizontally on narrow screens. This is a procurement workflow, with limits agreed by the responsible engineering team.

Supplier decision gates: Mandatory requirements — Demonstrated / open / failed — Engineering and quality; Weighted comparison — Agree program weights — Evidence behind scores; Award and release — Close assigned actions — Customer authorization

Editorial procurement worksheet. Unknown commercial and acceptance values require supplier evidence and customer agreement.

Table 4: Supplier capability audit worksheet
AreaEvidence to inspectEscalate when
MaterialGrade/lot storage and traceabilityMaterial cannot be traced to delivered parts
ManufacturingMaterial-specific process controlsSupplier cannot demonstrate reproducibility
Thermal processingQualified recipe and process recordsActual route differs from validated route
FinishingDimensional and magnetic checks after finishingCut/grind/coating effects are unverified
LaboratoryCalibrated methods or qualified external labMethods do not match the material or requirements

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Recommended procurement action: Hold a cross-functional award review using evidence and open actions, then obtain the required release.

Six Illustrative OEM Sourcing Scenarios

Hypothetical planning exercises, not customer projects or measured procurement outcomes. Volumes are illustrative assumptions; each plan describes evidence required before a sourcing decision.

Hypothetical high-voltage traction program

YASA (Yokeless & Segmented Armature) · SMC (Soft Magnetic Composite) · 15,000 units/yr · Customer requirements to confirm

Sourcing challenge: Oil-cooled segmented teeth; geometry and insulation qualification remain open.

Proposed validation plan: Compare pressing/finishing offers, measure processed-core properties, and validate the complete insulation and retention stack before award.

Hypothetical commercial drive ramp

SSDR (Single Stator Double Rotor) · SMC Segmented Ring Core · 50,000 units/yr · Customer requirements to confirm

Sourcing challenge: Growing demand with uncertain cavity economics and yield.

Proposed validation plan: Request comparable accepted-set quotes at forecast quantities; prove capacity and customer approval before committing production tooling.

Hypothetical aerospace propulsion program

DSSR (Double Stator Single Rotor) · Segmented electrical steel; grade/thickness to confirm · 800 units/yr · Customer requirements to confirm

Sourcing challenge: Traceability and flight-critical qualification evidence are not yet defined.

Proposed validation plan: Agree customer approval, FAI revision and structural/electrical test obligations; QMS certification alone cannot establish airworthiness.

Hypothetical compact robot joint

YASA (Ultra-Thin Axial Length) · High-Permeability SMC · 2,500 units/yr · Customer requirements to confirm

Sourcing challenge: Thin sections may complicate pressing, handling and assembly fits.

Proposed validation plan: Trial representative geometry, inspect ejection damage and correlate loss/strength before selecting the process route.

Hypothetical high-frequency blower

Slotless with magnetic back iron · Fe-Based Amorphous Ribbon · 500 units/yr · Customer requirements to confirm

Sourcing challenge: Slotless design retains magnetic back iron; ribbon performance under assembly stress is unknown.

Proposed validation plan: Compare grade-specific loss at the intended duty points and after encapsulation. If fully coreless, remove the stator core from the RFQ.

Hypothetical marine prototype

SSDR Rim Motor · Encapsulated SMC Potted Teeth · 25 units/yr · Customer requirements to confirm

Sourcing challenge: A low-volume sealed assembly needs corrosion, thermal and retention validation.

Proposed validation plan: Compare feasible prototype routes and compatible encapsulation; obtain a supplier schedule and test plan rather than assuming tool-free manufacture.

Technical & Commercial Sourcing FAQ

Sourcing Strategy & Supplier Selection

Can a radial-motor lamination supplier make AFPM cores?

Possibly. Evaluate the actual axial-core geometry, strip orientation, stacking, finishing and inspection capability. Powder presses are relevant only when the selected route needs powder compaction.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

What volume justifies a production die?

There is no universal threshold. Compare extra fixed investment against positive unit savings at the same accepted-part basis, including yield, maintenance, requalification and revision risk.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

How do we distinguish a manufacturer from an intermediary?

Identify which site performs each operation and who controls quality and traceability. Request process records and an audit of critical subcontractors; an intermediary is not automatically incapable.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Should we buy bare cores or a full stator?

Compare interface ownership, internal assembly capability, qualification cost and scrap responsibility. The tool adds insulation checks for insulated parts and winding/potting checks for full stators.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Does a second region guarantee supply resilience?

No. Verify independent capacity, material availability, tools and customer approval. Shared upstream sources can leave both regions exposed to the same interruption.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Tooling, NRE & Prototyping

How long does production tooling take?

Unknown until a dated offer defines design release, tool construction, trials, corrective work, sampling and customer approval. This tool does not publish an unsupported lead-time range.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Can prototype SMC parts be machined from blanks?

Ask the supplier to prove blank availability, machinability and post-machining magnetic/mechanical properties for the chosen grade. A generic blank route is not guaranteed for every geometry.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Can die material guarantee a fixed stroke life?

No. Wear depends on powder, geometry, lubrication, pressure, clearances and maintenance. Require cavity-level quality trends and agreed refurbishment/stop criteria.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Does paying NRE automatically transfer tooling ownership?

Ownership, use, access and relocation rights need explicit contractual terms. Have the responsible commercial/legal team review the agreement; a paid invoice alone is insufficient evidence.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

How should springback be handled?

Measure it on representative parts and refine the tooling against the approved process. Keep grade, pressure, temperature and metrology conditions traceable rather than using a universal compensation factor.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

How do we verify finishing has not increased loss?

Compare representative material/parts before and after the qualified finishing route under matched test conditions. Validate any deburring or passivation against the coating system instead of prescribing acid treatment universally.

Scope references (editorial actions require project validation): Höganäs — effect of manufacturing processes on coated SMC

Quality, Testing & Automotive PPAP

Is PPAP Level 3 mandatory for every automotive core?

Confirm the submission level and applicable records with the customer. Level 3 is a planning example here; certification, part submission and production release are separate checks.

Scope references (editorial actions require project validation): AIAG PPAP-4 — Production Part Approval Process

Can a companion ring approve every finished tooth?

It can monitor material/process consistency, but needs correlation to finished-part effects such as density gradients, machining and assembly stress. Agree sampling and acceptance separately.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

What pole-face flatness should we specify?

Derive it from the assembly clearance budget, deflection, thermal growth and measurement uncertainty. Flatness and runout are distinct, and no universal value is provided by this tool.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Which NDT method should screen cracks?

Select a method through representative defect trials and demonstrated detection capability. CT, acoustic or other inspection may be useful, but none guarantees detection of every microcrack in every geometry.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Does UL 1446 prove inverter insulation suitability?

System material compatibility and thermal evidence are useful, but must be checked for the actual application. PWM electrical stress needs the appropriate system qualification, not only a generic resin or coating label.

Scope references (editorial actions require project validation): UL Solutions — electrical insulation systems and UL 1446

Does this page calculate VDA 6.3 starred-question downgrades?

No. Use the licensed contracted edition, official interpretations and a competent auditor. The worksheet provides preparation topics without inventing official powder-specific question numbers.

Scope references (editorial actions require project validation): VDA 6.3:2023 — official sanctioned interpretations and FAQs

Does an 800 V bus specify the required PDIV?

No. Terminal waveform, rise time, cable effects, temperature, altitude and insulation-system category matter. The electrical engineer and lab must define qualification and routine tests for the system.

Scope references (editorial actions require project validation): IEC 60034-18-41:2014+AMD1:2019 — Type I insulation systems

Which magnetic method applies to electrical steel?

Discuss an electrical-steel method such as IEC 60404-2 for sheet/strip. IEC 60404-6 excludes electrical steels. Establish an agreed correlation between material specimens and delivered cores.

Scope references (editorial actions require project validation): IEC 60404-2 — electrical steel sheet/strip measurement · IEC 60404-6:2018 — AC ring measurement methods

Commercials, Lead Times & Contracts

What share of unit price is raw material?

Unknown without a supplier cost breakdown. Request mass, yield, conversion, finishing, inspection, tooling recovery and delivery on one accepted motor-set basis.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

How should material indexation be negotiated?

Agree a relevant index, base date, material share, update interval and verification method. A steel commodity index may not track a processed insulated powder; no universal trigger is assumed.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

What information makes quotations comparable?

Controlled CAD and drawings, individual part quantities, grade and test conditions, duty envelope, delivery scope, customer approval requirements and a dated volume/ramp schedule.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Which NRE payment milestones should we use?

Negotiate measurable milestones such as design review, tool trials, sample acceptance and required customer release. Percentages and payment dates are contract-specific, not set by this page.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Can we substitute a nominally equivalent SMC powder?

Only after the agreed material/process/assembly qualification and required customer change approval. Similar family names or a single magnetic measurement do not prove interchangeability.

Basis: editorial procurement guidance. Validate against the project specification; no universal acceptance limit or commercial dataset.

Primary Standards & Evidence Ledger

Scope checked 2026-11-05. Links identify primary publications and manufacturer guidance; public abstracts do not substitute for the licensed standards. Each scope note states its applicability and limits. Customer approval requires the agreed submission and release process, not completion of this checklist.

IEC 60404-6:2018 — AC ring measurement methods

AC ring testing from 20 Hz to 100 kHz for covered soft metallic and powder materials; explicitly excludes electrical steels and soft ferrites. Confirm amendments and material applicability with the laboratory.

Submit Your AFPM Core Technical Data Package for Review

Send your 3D CAD STEP file, GD&T drawings, target volume ramp, and magnetic performance envelope. Request a review of material and tooling feasibility, delivery scope and the open qualification requirements. Confirm the review scope and available manufacturing capability before relying on any commercial or technical commitment.

Direct inquiry contact: [email protected]